21st Street Receives Drainage Improvements

click on photo to expand
Construction crews are creating a shoulder on the north side of 21st Street just west of Country Club Rd.

Photo by Linda Thompson
(posted 7.11.09)

The 21st Street storm water drainage project is scheduled to be completed by July 17. The open ditch is being enclosed with the installation of drainage pipes. "This project site is part of the 2008 Miscellaneous County Wide Stormwater Improvements, Phase II project," DPW PIO Kit Werbe said.

The drainage improvements will occur on the north side of 21st Street from 8344 to 8556. "The cost of construction for this site is approx. $100,000," she said. The total project is $677,000.