| |
DPW Approves Roundabout Concept
(posted Feb 13)
Despite assurances to the Speedway Town Council that the 16th and Main
Street roundabout has been approved, the Department of Public Works has
not given it's final blessing to the project.
Speedway Redevelopment Commission Executive Director Scott Harris told
the council at its February 9 meeting that "We have received engineering
approval for the roundabout design. The right-of-way engineering has been
completed on that set of parcels this week."
On February 11 DPW spokesperson Kit Werbe stated “both the realignment
and the roundabout have not been officially approved. The concept has been
approved for both the realignment and for the roundabout. But, the final
design plans have not been approved. That's why I have to say that at this
time, neither item has been approved.”
|
|